![]() |
||
| PART 3 | ||
| Background | Forms of Response |
Features of Response |
Institution and Management |
| Rosters | Emerging Issues | Resources | Processing Steps |
· Lead disaster agency
· Policy makers
Under the policy, the Bank may provide a rapid response to a borrower’s request for urgent assistance to address an event that has caused, or is likely to imminently cause, a major adverse economic and/or social impact associated with natural or man-made crises or disasters.
OP/BP 8.00 is premised on principles that include (1) the need to focus Bank assistance on its core development and economic competencies while remaining within its mandate; (2) establishment of appropriate partnership arrangements with other development partners, including the United Nations (UN); and (3) adoption of adequate oversight arrangements.
Objectives. The Bank may provide rapid response in support of one or more of the following objectives:
Recipient. The Bank’s assistance should be focused in its core development and economic competencies, and may include
The Bank recognizes the lead of other international institutions, in particular the UN, in such activities, and forms partnership arrangements with other donors for the preparation, appraisal, and supervision of activities outside its core competencies.
Simplified, streamlined procedures are processed under accelerated and consolidated procedures and are subject to streamlined ex-ante requirements (including in fiduciary and safeguards areas).
Risk management involves a different balance between ex-ante and ex-post controls and risk mitigation measures compared to regular operations, including on issues of fraud and corruption, requiring intensified supervision support to address such risks.
Financing percentage. Unless the country director determines otherwise, include Bank financing of up to 100 percent of the expenditures needed to meet the development objectives of such operations, including recurrent expenditures, local costs, and taxes.
Retroactive financing may include up to 40 percent of the loan amount for payments made by the borrower not more than 12 months prior to the expected date of signing the legal documents.
Larger Project Preparation Advance (PPA) limit may benefit from a PPA of up to US$5 million to cover start-up emergency response activities.
Quick disbursement and streamlined procedures may include a quick-disbursing component designed to finance a positive list of goods, (1) required for the borrower’s emergency recovery program and (2) procured following procedures, that satisfy the requirements of economy and efficiency (normally the national emergency procurement procedures of the borrower). Streamlined financial management, procurement, and disbursement procedures may include:
Initiation and Management of Bank Response[1]
Otherwise, an RRC is convened under the chairmanship of the RVP or the CD, depending on the nature of the emergency and/or the extent to which interdepartmental resource transfers are necessary. The RRC may assist in identifying and supplementing staff to prepare and implement the Bank’s response, including from the callable roster.
OP/BP 8.00 identifies the steps involved once the policy has been triggered. These include the following.
Internal Communications. The Regional Vice President (RVP) communicates with the Managing Director (MD) of the affected region, the Chief Financial Officer (CFO) and VP (OPCS); and, depending on the nature of the emergency, the Conflict Prevention and Reconstruction Unit (CPR), the Fragile States Unit (OPCFS) and the Hazard Management Unit.
Establishment of a Rapid Response Committee (RRC). An RRC is immediately convened by the responsible MD in the case of corporate emergencies.
Processing Timelines. For emergency projects of a simple design, task teams should aim to seek Board approval within 10 weeks of initiation of project discussion with government. For simple project restructuring, task teams should aim to seek approval within 4 weeks. (Detailed processing steps and turnaround times are found in the annex to this chapter.)
In an effort to improve the availability and readiness of experienced staff and consultants to deploy on short notice, a Staff Roster has been established with staff registered from 20 sectors or units of the Bank, as of late2009. This can be accessed through a Bank staff member to identify expertise in response to requests from country units or governments.
A Consultant Roster is also being developed, to improve the sharing of expertise with bilateral and multilateral agencies.
World Bank. "Guidelines: Financial Management Aspects of Emergency Operations Processed under OP/BP 8.00."
World Bank. 2007. Operational Manual. “Operational Policy (OP) 8.00, Rapid Response to Crises and Emergencies.” http://go.worldbank.org/54R3G3UES0.
World Bank. 2007. Operational Manual. “Bank Procedures (BP) 8.00, Rapid Response to Crises and Emergencies.” http://go.worldbank.org/ILPIIVUFN0.
World Bank. 2007. "Processing Projects under OP/BP 8.00. Additional Guidance Note #1."
World Bank. 2009. "Processing Projects under OP/BP 8.00: A Review of Early Experience and Lessons Learned. Note of Discussion".
World Bank. 2008. Rapid Response to Crises and Emergencies: Application of Bank Safeguard and Disclosure Policies. Note.
World Bank. "Rapid Response to Crises and Emergencies: Procedural Guidelines."
A. Emergency Recovery Loan—Identification to Effectiveness
|
Step
|
Guidelines
|
Primary responsibility
|
Turnaround
(working days) |
|
Identification/
approval of proposal |
Team Leader (TL) obtains the agreement of the CD on the project’s outline and budget and informs OPCS of the team’s intention to launch a new emergency operation. At the same time, the TL alerts regional designated emergency staff (FM, Procurement [PR], Legal, Loan Department [LOA], and Safeguards).
|
CD/TL
|
|
|
Project Information Document (PID), Integrated Safeguards Data Sheet (ISDS)
|
TL prepares a draft PID and a draft ISDS, both of which are updated throughout the process.
|
TL
|
|
|
Combined preparation/
appraisal mission |
During a combined preparation-appraisal mission, the task team (TT) assists the borrower in preparing the new project.
|
TL/TT
|
|
|
Drafting of Emergency Project Paper (EPP) and Simplified Procurement Plan (SPP)
|
The TT prepares the EPP[4] with the relevant annexes on procurement (including a SPP), financial management, and safeguards.
|
TL/TT
|
|
|
Drafting of legal agreement
Review by safeguards coordinator |
The TL provides the designated lawyer with a copy of the EPP for drafting the legal agreement and the safeguards coordinator with a copy of the draft ISDS for confirming environmental assessment (EA) category review, comment, and clearance authority.
Input from the safeguards coordinator may include, for example, key safeguard issues to consider, other safeguard policies triggered (e.g. cultural properties, natural habitats) and the form of EA document (framework, Cat A environmental impact assessment, environmental management plan (EMP), etc.). |
Lawyer
Safeguards Coordinator
|
2
|
|
Review of draft legal agreement and EPP by PR, FM, and LOA.
|
The TL shares a copy of the EPP and the draft legal agreement with assigned staff from PR, FM, and LOA for their inputs and preparation of necessary documentation, including the disbursement letter and procurement provisions of legal agreement.
|
PR
FM
LOA
|
2
|
|
Finalization of review package
|
The lawyer finalizes the package based on inputs from PR, FM, and LOA.
|
Lawyer
|
1
|
|
Submission of review package to CD
|
When TL determines that the information reflected in project documents (draft EPP, draft legal agreement, SPP, and draft disbursement letter) forms a sufficient basis to enter into negotiations, the TL submits the entire package to the CD for a formal decision meeting.
|
TL
|
|
|
Decision meeting
|
The RVP or designee convenes a decision meeting to review the package. Unless the meeting concludes that the project is not ready for further processing, the decision meeting authorizes the TL to proceed with negotiations with the borrower.
Minutes of the meeting record clearances provided by FM, PR, and LOA, and any conditions for agreement with borrower.
|
CD
|
Within 3 days of circulation of documents
|
|
Circulation of minutes of meeting
|
TL clears with the chair and circulates minutes of meeting on a no-objection basis.
|
TL
|
Objections submitted within 1day
|
|
Finalization of negotiations package
|
Based on the decision meeting’s recommendations, the TL works closely with the lawyer, Finance Officer, and fiduciary staff to finalize the negotiations package, including a revised EPP, draft legal documents and the disbursement letter, ISDS, and PID.
|
TT and lawyer
|
Within 3 days of meeting, unless additional work with borrower is required
|
|
Submission of PID and ISDS to World Bank Infoshop
|
TL submits PID and finalized ISDS to Infoshop
|
TL
|
|
|
Invitation to negotiate
|
TL sends the negotiations package to the borrower with an invitation to negotiate and informs the Secretary of the Board in writing of the schedule.
|
TL
|
|
|
Negotiations
|
Draft legal agreements are agreed to and minutes of negotiations are signed.
At negotiations, the TL also tries to (1) obtain from the borrower the authorization of signature, (2) arrange for signature of Statutory Committee Report/Recommendation, and (3) discuss with the borrower the format of the legal opinion. TL also obtains from borrower information about the Designated Account information.
|
TL
|
|
|
Finalize Board package
|
TL and lawyer finalize the Board package based on minutes of negotiations.
|
TL/lawyer
|
2
|
|
Board approval
|
RVP (or CD, where delegated) submits Board package to the Secretary of the Board (SECBO) for Board approval on a streamlined basis.
TL requests Trust Funds Division of Accounting Department (ACTTF) to generate information on status of borrower’s services payments.
|
RVP’s
(or CD’s) office |
Documents to SECBO 10 days before Board
|
|
Notification of approval
|
TL prepares a notification of approval and sends it to the borrower.
|
TL
|
1 day after Board date
|
|
Signing
|
TL arranges for CD/borrower signature of legal documents, including the legal opinion.
If there are no additional conditions of effectiveness, a notice of effectiveness is prepared and signed by the CD.
|
TL/CD
CD’s office
|
Same day as signature of legal documents
|
|
Notification of effectiveness
|
If there are additional conditions for effectiveness, the TL monitors progress toward them and submits to the designated lawyer the effectiveness package, including evidence of compliance with conditions.
Once the lawyer clears the effectiveness package, the TL prepares for the CD’s signature a letter confirming acceptance of the required evidence of compliance and declares the legal agreement effective. The notice is copied to the FM.
|
Lawyer
TL/CD
|
Lawyer clearance of compliance evidence within 2 days of submission by TL
|
|
Step
|
Guidelines
|
Primary responsibility
|
Turnaround (working days)
|
|
Identification
|
TL prepares a proposal for restructuring/additional financing in a concept memorandum and sends it to the CD.[5]
|
TL
|
|
|
Approval of proposal:
the CD obtains the agreement of the regional management on the level of approval likely to be required for the project’s restructuring and on the amount of additional resources necessary for the restructuring work (including for appraisal)
|
At this point, OPCS is informed of the team’s intention to launch a new emergency operation and regional designated emergency staff (FM, PR, Legal, LOA, and Safeguards) are alerted.
|
CD/TL
|
2
|
|
Drafting of Restructured Project Paper (PP)/Additional Financing Project Paper (APP), ISDS, and Procurement Plan
|
TT
|
|
|
|
Drafting of legal amendment
Drafting of Procurement Plan
Review by safeguards coordinator
|
The TL provides the designated lawyer with a copy of the appropriate project paper for drafting the necessary amendments and the designated procurement specialist with a revised Procurement Plan for clearance.
If the ISDS is revised, a copy of it is shared with the safeguards coordinator for review and comment, confirmation of EA category, and a decision regarding delegation of authority.
|
Lawyer
PAS
Safeguards Coordinator
|
2[8]
|
|
Review of draft amendment by PR, FM, and LOA
|
The TL shares a copy of the project paper and the draft amendments with assigned staff from PR, FM, and LOA for their inputs and preparation of necessary documentation, including the disbursement letter and procurement provisions of legal amendment.
|
PR
FM
LOA
|
1
|
|
Finalization of review package
|
When amendments to the legal documents are required, the lawyer finalizes the amendments to the legal agreement.
|
Lawyer
|
1
|
|
Submission of review package to CD
|
When TL determines that the information reflected in project documents (draft APP, draft legal amendment, revised procurement plan, and revised Disbursement Letter) forms a sufficient basis to enter into negotiations, the TL submits the entire package to the CD for a formal decision meeting.
|
TL
|
|
|
Decision meeting
|
The RVP or designee convenes a decision meeting to review the package and authorize agreement with the borrower. Minutes of the meeting record clearances provided by FM, PR, and LOA and any conditions for agreement with borrower.
|
CD
|
Within 3 days of circulation of documents
|
|
Circulation of minutes of meeting
|
TL clears with the chair and circulates minutes of meeting on a no-objection basis.
|
TL
|
Objections submitted within 1 day
|
|
Finalization of negotiations package
|
The lawyer finalizes the draft agreement, taking into account the minutes of the decision meeting.
|
Lawyer
|
1
|
|
Agreement with borrower on PP/APP and legal agreement
|
Agreement is reached with the borrower on the legal amendment/PP and APP.
|
TL
|
|
|
Submission of PID and ISDS to Infoshop
|
As necessary, TL submits the revised PID and ISDS to Infoshop.
|
|
|
|
Finalize Board package
|
TL prepares the PP package, consisting of the Memorandum and Recommendation of the President (MOP), data sheet, and PP.
|
TL
|
1
|
|
Board approval
|
RVP (or CD, where delegated) submits Board package to SECBO for Board approval on a streamlined basis.
|
RVP’s (or CD’s) office
|
For additional financing projects, documents sent to SECBO 10 days before Board
|
|
Signing
|
Upon approval, the CD signs amendment letter. Signed amendment letter sent to borrower for countersigning.
|
CD
CD’s office
|
1
|
|
PID
|
If necessary, TL revises (and CD clears) the PID, and TL sends revised PID to Infoshop.
|
TL
|
2
|
[1]. A “corporate emergency” is one that requires the mobilization of technical, financial, or institutional resources that are beyond what the RVP can provide and/or involve a degree of reputational risk that argues for a corporate review or response.
[2]. World Bank, 2009, “Rapid Response to Crises and Emergencies (OP/BP 8.00): Progress Report (Draft),” World Bank internal report.
[4]. A format for the EPP is available from the Loan Department.
[5]. The memo includes an outline of the restructuring, a proposed budget, and a definition for additional staffing for discussion/preparation.
[6]. Designated emergency staff from FM, PR, Legal, Loan, and Safeguards should be copied on all correspondence related to project documentation.
[7]. For a template and guidelines on documentation used for restructuring and additional financing, staff may refer to (1) “Processing Restructuring for Investment Projects: Guidelines for Staff” and (2) Processing Additional Financing: Guidance to Staff.
[8]. If more than one amendment is necessary, additional time may be needed.
| Safeguards Policy Objectives | Environmental Safeguards for Normal Operations | Case Studies |
| Challenges in Developing ESSAFs | Environmental Safeguards for Emergency Loans | Safeguard Policy Summaries |
· Policy makers
· Lead disaster agency
This chapter is intended to provide guidance on the application of World Bank safeguards in post-disaster projects. It contains (1) a review of environmental and social safeguards procedures for normal operations, (2) a review of environmental and social safeguards procedures for post-disaster operations, (3) observations about the implementation of safeguards, and (4) case studies related to specific operations. It also includes links to the formats needed to prepare various documents required in the post-disaster environmental and social review process.
The World Bank’s environmental and social safeguard policies are a cornerstone of its support to sustainable poverty reduction. The objective of these policies is to prevent and mitigate undue harm to people and their environment in the development process. These policies provide guidelines for Bank and borrower staffs in the identification, preparation, and implementation of programs and projects.
The Bank believes that the effectiveness and development impact of projects and programs it supports has substantially increased as a result of attention to these policies. Safeguard policies also provide a platform for the participation of stakeholders in project design and have been an important instrument for building a sense of ownership among local populations.
In essence, the safeguards ensure that environmental and social issues are evaluated in decision making, help reduce and manage the risks associated with a project or program, and provide a mechanism for consultation and disclosure of information. The safeguards are listed below. More detailed summaries of selected safeguard policies are included in the annex, Safeguard Policy Summaries.
|
OP/BP |
Safeguard |
Policy objectives |
|
4.01 |
Environmental Assessment* |
Help ensure the environmental and social soundness and sustainability of investment projects. Support integration of environmental and social aspects of projects in the decision-making process. |
|
4.04 |
Natural Habitats* |
Promote environmentally sustainable development by supporting the protection, conservation, maintenance, and rehabilitation of natural habitats and their functions. |
|
4.09 |
Pest Management |
Minimize and manage the environmental and health risks associated with pesticide use and promote and support safe, effective, and environmentally sound pest management. |
|
4.11 |
Physical Cultural Resources (PCR)* |
Assist in preserving PCR and in avoiding their destruction or damage. PCR includes resources of archeological, paleontological, historical, architectural, religious (including graveyards and burial sites), aesthetic, or other cultural significance. |
|
4.12 |
Involuntary Resettlement* |
Avoid or minimize involuntary resettlement and, where this is not feasible, assist displaced persons in improving or at least restoring their livelihoods and standards of living in real terms relative to pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher. |
|
4.20 |
Indigenous Peoples* |
Design and implement projects in a way that fosters full respect for indigenous peoples’ dignity, human rights, and cultural uniqueness and so that they (1) receive culturally compatible social and economic benefits, and (2) do not suffer adverse effects during the development process. |
|
4.36 |
Forests* |
Realize the potential of forests to reduce poverty in a sustainable manner, integrate forests effectively into sustainable economic development, and protect the vital local and global environmental services and values of forests. |
|
4.37 |
Safety of Dams |
Ensure quality and safety in the design and construction of new dams and the rehabilitation of existing dams, and in carrying out activities that may be affected by an existing dam. |
|
7.50 |
Projects on International Waterways |
Ensure that the international aspects of a project on an international waterway are dealt with at the earliest possible opportunity and that riparians are notified of the proposed project and its details. |
|
7.60 |
Projects in Disputed Areas |
Ensure that other claimants to the disputed area have no objection to the project, or that the special circumstances of the case warrant the Bank’s support of the project notwithstanding any objection or lack of approval by the other claimants. |
The table below outlines the requirements for each of these elements.
|
EA policy element |
Policy requirement |
Comment |
|
1. Screening |
Projects are categories as: Category A (high risk-- likely to have significant adverse environmental impacts that are sensitive, diverse, or unprecedented) Category B (modest risk-- potential adverse environmental impacts on human populations or environmentally important areas--including wetlands, forests, grasslands, and other natural habitats--are less adverse than those of Category A projects) Category C (likely to have minimal or no adverse environmental impacts), or Financial Intermediary (FI) operation (involves investment of Bank funds through a financial intermediary, in subprojects that may result in adverse environmental impacts) |
Project assessed a priori, depending on estimated environmental risk |
|
2. Documentation |
Category A, Detailed Environmental Impact Assessment (EIA) Category B, Environmental Management Plan (EMP) Category C, No requirement Category FI, Environmental Framework |
Format presented in OP 4.01 (Annex B) Format presented in OP 4.01 (Annex C) [2] Specific investments unknown before project implementation. Documentation includes requirements for subproject EA. Environmental Framework describes EA process. Loan conditions include obligation for effective supervision and monitoring of EMP implementation. Sector investment loans may have similar requirements. |
|
3. Consultation |
Category A At least two consultations Category B At least one consultation |
Consultations are conducted to receive input from local affected groups on their views of important environmental issues |
|
4. Disclosure |
Category A At the World Bank Infoshop (English) In-country, accessible to local affected groups (local language) Category B In-country, accessible to local affected groups (local language) Category FI Framework disclosed at the World Bank Infoshop and appropriate in-country Web site (e.g. Ministry of Environment). Individual subproject disclosure requirements defined in Framework |
|
|
5. Review and approval |
Category A Regional Safeguards Coordinator Category B Sector Manager or Regional Safeguards Coordinator Category FI Framework reviewed/approved by Regional Safeguards Coordinator; individual subproject review and approval arrangements defined in Environmental Framework |
Depends on whether project is “delegated” |
|
6. Conditionality |
Borrower is obligated to implement EMP (Category A or B) |
|
|
7. Supervision, monitoring, and reporting |
Category A, B, or FI Institutional arrangements defined in EA documentation (EIA, EMP, or Framework) |
|
Generally speaking, Emergency Recovery Projects are not exempt from the World Bank EA Policy (see OP 4.01, paragraph 13). Under unusual circumstances, a project may be exempted, but this requires a formal process and the justification must be recorded in the loan documents. If any waivers or exemptions from OP/BP 8.00 are required, the Task Team Leader should seek approvals prior to loan negotiations.
Determine country-specific policies and regulations for environmental safeguards (primarily EA) in emergency/disaster situations. If such information is not available, LEGEN should provide the Task Team with the primary government contacts who have this information.
During the combined preparation-appraisal mission, the Task Team Safeguards Specialist will take the following steps.
Upon mission completion, the Task Team Safeguards Specialist will take the following steps.
Legal agreements must include obligations of the borrower to implement the requirements specified in the EA documents.
For subprojects not known at the time of loan approval. An ESSAF is required for these loans. The environmental portion of the ESSAF describes EA safeguard review procedures to be followed as subprojects are identified and considered for financing. This framework should have the following characteristics.
ESSAF preparation. The ESSAF document is a unique World Bank safeguard requirement.[4] Unless the host country already has had a World Bank disaster operation, host country institutions involved with disaster operations (Ministry of Housing, Ministry of Finance, etc.) are normally not familiar with World Bank safeguard requirements and would likely take a very long time to produce the ESSAF document by themselves, likely involving several iterations. Furthermore, host countries do not usually place a high priority on environmental and social safeguard issues during disaster situations, and the ESSAF document is often viewed as an obstacle to receiving the immediate assistance they need.
Forcing attention on these concerns may be extremely frustrating to all parties concerned and could affect the relationship between the host government and the World Bank. Therefore, the Bank team should either prepare the draft ESSAF for the host country review and approval or work closely with the host country in preparing the ESSAF document.
At least one public consultation with affected groups should be conducted as part of ESSAF preparation to ascertain priority issues. This will help identify the need for safeguard policies other than EA and resettlement being triggered (e.g., natural habitats, cultural properties).
ESSAF capacity assessment. As part of the ESSAF preparation, the World Bank team should conduct a capacity assessment of the institutions that will be responsible for ESSAF implementation to determine if there is sufficient staff/expertise/authority to implement ESSAF requirements.
It is strongly recommended that such an assessment be done ex-ante in countries prone to natural disasters (in this way valuable time in a disaster operation will not be spent on preparing a capacity assessment evaluation).
ESSAF implementation. The ESSAF requirement is relatively new, and implementation experience in practice has so far not been exemplary. It is a critical aspect of World Bank safeguards to ensure proper supervision and follow-up of ESSAF implementation.
In disaster situations, host governments will generally agree initially to the Bank’s environmental requirements in the interest of getting access to the resources that are needed to address the disaster. Without guidance on ESSAF implementation and attention from the World Bank, ESSAF requirements may be forgotten during project implementation.
If there is a Project Implementation Unit (PIU), the project team should require an environmental and/or a social safeguards specialist be included on the PIU staff, either a staff person or an experienced consultant. The PIU should issue regular, frequent reports to affected groups and implementing institutions on any environmental or social issues that arise, measures taken to address these issues, parties responsible for addressing the issues, and a schedule for their resolution. The PIU should also issue regular and frequent information to affected groups regarding vital services, such as safety of water supply, and interim arrangements for wastewater management and solid waste disposal.
The government of Sri Lanka asked, inter alia, the World Bank for assistance in conducting a damage assessment and, simultaneously, worked with the World Bank to prepare a restructuring operation: “Tsunami Emergency Recovery Program – Phase I.”
Design and preparation. Safeguard policies as required by the World Bank were adequately designed into the project framework. An Environmental and Social Screening and Assessment framework (ESSAF) was prepared. The framework was designed to help government properly address and mitigate safeguard issues. For environmental risks, this included an assessment of governments’ review and approval process for EIAs and of its capacity to monitor implementation of environmental mitigating measures.
Implementation. The period after the tsunami saw a boom in reconstruction activities across the country. Government adopted a policy of “build back better.” As a consequence, the opportunity to integrate cross-cutting ecological and environmental concerns was lost. After the disaster, government announced the use of a buffer zone as a disaster prevention mechanism. This was most likely done as an immediate response and was not based on sound technical judgment or on public consultation. The resulting effects on the environment were profound. With physical reconstruction prohibited in the “no build zone,” vast extents of new hinterland (including some natural areas) were cleared for proposed housing schemes. No system of EA was involved with the site selection and construction process; environmental planning took a low priority. The policy was later withdrawn and the Coast Conservation Department developed a more reasonable Coastal Zone Management Plan.
Key environmental issues included those associated with extraction of natural resources as construction materials. Reconstruction created a building boom of unprecedented scale and a high demand for sand, timber, rubble, and clay, among other resources. There was no system in place to verify the origin of these materials, even though sources were identified in the EIAs. As a consequence, much of this material was extracted illegally. Although the EIAs discussed removal of debris, by the time the EIAs were mobilized, debris had already been removed and used for roads and landfill. This gave rise to adverse drainage issues in some locations.
In summary, the project did include environmental safeguards as required. However, post-clearance monitoring and secondary impacts were not properly anticipated or addressed.
1999 Marmara Earthquake Emergency Reconstruction Project, Turkey
Context. On August 17, 1999, an earthquake measuring 7.4 on the Richter scale devastated the Marmara region of Turkey. More than 15,000 lives were lost and about 200,000 people were left homeless.
The World Bank undertook an assessment to outline the likely impact of the earthquake on the economy and estimated the fiscal burden for reconstruction and recovery in the range of US$1.8–US$2.2 billion. The largest direct cost (US$0.7–US$1.2 billion) was for reconstruction and repair of the region’s housing stock.
Design and preparation. The main objectives of the program were to restore living conditions in the affected region of Marmara, support economic recovery and growth, and develop an institutional framework for disaster risk management and mitigation.
Investments included housing replacement or reconstruction and restoration of sports fields, playgrounds, and other common spaces. Feedback from housing reconstruction beneficiaries received during public consultations soon after the disaster led to design changes in the housing units. Monitoring and evaluation activities of the Project Implementation Unit (PIU) and consultant reports resulted in additional public outreach efforts to the beneficiaries of the rural housing reconstruction component. A monthly newsletter was published and distributed by the PIU at the earthquake reconstruction project sites. This allowed for further adjustments and reallocations during project implementation.
Implementation. The project was developed with full compliance with the World Bank safeguard policies in effect at the time of preparation (EA and involuntary resettlement). During preparation, sites proposed by government for urban housing were planned on public land, but early in the implementation process it was clear that some expropriation would be needed. The Task Team did due diligence and proceeded in compliance with the requirements of OP 4.12, including adherence to the Resettlement Plan and close supervision of compensation. Regular site visits were made by the PIU’s social scientist.
Environmental safeguards were also monitored closely by the PIU, its local branches, and the World Bank Task Team with respect to compliance with the Environmental Management Plan. The PIU had well-qualified engineers, provided environmental training to the contractors, and had a constant presence at the construction sites. Monthly environmental reports were prepared and submitted to the World Bank for review. Both the PIU and the World Bank were actively involved in ensuring high environmental standards for the reconstruction, exemplified by careful attention to the construction of a sewage treatment plant to ensure adequate treatment before municipal sewage from the housing complex near Golcuk was discharged into the Bay of Izmit. Also, as a result of careful site monitoring, additional measures for erosion control were introduced.
1999 Armenia Earthquake Recovery Project, Colombia
Design and Preparation. Within a week of the disaster, international donors and nongovernmental organizations assisted with immediate needs (clearing debris and temporary shelter). The World Bank was involved in the medium- and longer-term reconstruction program. Four existing World Bank loans (Municipal Health Services, Secondary Education, Agricultural Technology Development and Urban Environmental Management) were restructured for this project (totaling US$93 million).
The government of Colombia established a Reconstruction Fund for the Coffee Region (FOREC) reporting to the country’s president. FOREC was to finance, execute, and coordinate the economic, social, and environmental reconstruction of the affected region. FOREC’s functions were to design operational guidelines for implementation of reconstruction activities, work with local mayors to provide a framework for reconstruction activities, and oversee the reconstruction effort.
The World Bank prepared the Earthquake Recovery Loan with an additional US$225 million to continue the reconstruction effort for repair of 509 schools, rebuilding of 142 schools, and repair of 74 hospitals and health centers.
Implementation. Government recognized immediately that the earthquake had caused a number of environmental problems, and the reconstruction process offered a number of opportunities to strengthen local environmental institutions and improve environmental management. A Regional Environmental Management Plan was ordered by presidential decree (1999) that was intended to ensure the reconstruction process (including debris removal) followed environmental safeguards and ensured environmental sustainability of natural resources. Environmental standards for reconstruction work were established, land use plans were prepared which, inter alia, identified high-risk areas that were not to be developed. The process included public participation. As a result of this effort, approximately 13,000 families had to be relocated from high-risk areas. This approach enhanced local government capacity for environmental management (e.g., debris handling, soil stabilization, drainage management).
As a result of these efforts, municipal administrations had a greater role in land use for public and social infrastructure works, and new housing was not placed in high-risk areas.
|
Natural Habitats (OP/BP 4.04)
|
|
This policy prohibits Bank support for projects that would lead to the significant loss or degradation of any Critical Natural Habitats, whose definition includes those natural habitats that are:
The policy is “triggered” if a subproject could result in any one or more of the following four events:
If, as part of the EA process described above and/or discussions with the Regional Safeguards Coordinator, the potential for significant conversion or degradation of critical or other natural habitats is identified (in accordance with one or more of the indicated criteria), the subproject is classified as Category A; projects otherwise involving natural habitats are classified as Category A or B, depending on the degree of their ecological impacts.
During the combined preparation-appraisal mission, the Task Team Safeguards specialist should meet with government environmental officials and verify whether or not natural habitats would be affected by the project. If natural habitats are involved, the manner in which the issue would be addressed should be described in the EA documentation.
|
|
Physical Cultural Resources (OP/BP 4.11)
|
|
This policy addresses PCR, which are defined as movable or immovable objects, sites, structures, groups of structures, and natural features and landscapes that have archeological, paleontological, historical, architectural, religious, aesthetic, or other cultural significance. They may be located in urban or rural settings, and may be above or below ground or under water. Their cultural interest may be at the local, provincial, or national level, or within the international community.
If the EA process described above or discussions with the Regional Safeguards Coordinator indicate a subproject (1) will involve significant excavations, demolition, movement of earth, flooding, or other environmental changes; or (2) will be located in, or in the vicinity of, a physical cultural resources site recognized by competent authorities of the borrower, the policy would be tentatively considered “triggered.”
During the combined preparation-appraisal mission, the Task Team Safeguard Specialist should meet with government competent authorities and verify whether physical cultural resources would be affected by the project. If it is verified that the project has any of the characteristics set out in (1) or (2) above, the policy is triggered and assigned to either Category A or B. The manner in which the issue would be addressed should be described in the EA documentation.
|
|
Forests (OP 4.36) |
|
This policy applies to the following types of Bank-financed investment projects:
The Bank does not finance projects that, in its opinion, would involve significant conversion or degradation of critical forest areas or related Critical Natural Habitats. If a project involves the significant conversion or degradation of natural forests or related natural habitats that the Bank determines are not critical, and the Bank determines that there are no feasible alternatives to the project and its siting, and comprehensive analysis demonstrates that overall benefits from the project substantially outweigh the environmental costs, the Bank may finance the project, provided that it incorporates appropriate mitigation measures.
The policy is “triggered” if any one of the following criteria is applicable.
For each project covered under the scope of the policy, World Bank staff ensure that an EA category is assigned in accordance with the requirements of OP/BP 4.01, Environmental Assessment. A project that is likely to have significant adverse environmental impacts with potential for conversion or degradation of natural forests or other natural habitats that that are sensitive, diverse, or unprecedented is classified as Category A; projects otherwise involving forests or other natural habitats are classified as Category B, C, or FI, depending on the type, location, sensitivity, and scale of the project and the nature and magnitude of its environmental impacts.
|
|
Indigenous People (OP/BP 4.20) |
|
This policy contributes to the Bank’s mission of poverty reduction and sustainable development by ensuring that the development process fully respects the dignity, human rights, economies, and cultures of indigenous peoples. For all projects that are proposed for Bank financing and affect indigenous peoples, the Bank requires the borrower to engage in a process of free, prior, and informed consultation.
A project proposed for Bank financing that affects indigenous peoples requires:
|
|
Resettlement (OP/BP 4.12) |
|
This policy covers direct economic and social impacts that both result from Bank-assisted investment projects and are caused by:
This policy applies to all components of the project that result in involuntary resettlement, regardless of the source of financing. It also applies to other activities resulting in involuntary resettlement that in the judgment of the Bank, are:
To address the impacts above, the borrower ordinarily prepares a resettlement plan or a resettlement policy framework (see paragraphs 25-30 of the policy) that covers the following:
Requests for guidance on the application and scope of this policy should be addressed to the Resettlement Committee (see BP 4.12, paragraph 7). |
[1]. World Bank, 1999, OP 4.01 “Environmental Assessment,” http://go.worldbank.org/9MIMAQUHN0 and BP 4.01 “Environmental Assessment,” http://go.worldbank.org/9MIMAQUHN0; and “Environmental Assessment Sourcebook and Updates,” http://go.worldbank.org/LLF3CMS1I0.
[2]. World Bank, 1999, OP 4.01 “Environmental Assessment, Annex C, Environmental Management Plan” http://go.worldbank.org/B06520UI80.
[3]. World Bank, “OP 8.00, Rapid Response to Crises and Emergencies,” http://go.worldbank.org/IKGMVADFB0 and “BP 8.00, Rapid Response to Crises and Emergencies,” http://go.worldbank.org/IE6E6NYJG1.
[4]. For samples of project ISDS documents, search in World Bank, “Documents and Reports,” under “Project Documents,” http://go.worldbank.org/XFNFIE0SO0.
[5]. See World Bank, “Rapid Response to Crises and Emergencies: Procedural Guidelines.”
| World Bank Project Cycle | Financial Management in Bank Operations |
| Issues in Emergency Operations |
Financial Management in OP/BP 8.00 |
· Policy makers
· Lead disaster agency
· Financial specialists
· Project managers
The World Bank recognizes that financial management is an integral part of the development process. In the public sector, it ensures accountability and efficiency in the management of country resources; in the private sector, it promotes investment and growth. Therefore, the first objective of the Bank’s attention to financial management is to improve borrowing countries’ FM performance. At the same time, if the Bank is to sustain the confidence of its shareholders, other stakeholders, and the public at large, it must be able to show that its funds are used appropriately. Thus, the second objective of the Bank’s financial management work is to provide acceptable assurance on the use of Bank loan proceeds. While these objectives are sought even in emergency operations, including post-disaster reconstruction projects, adjustments to normal procedures are sometimes required.
For the World Bank, financial management arrangements are the budgeting, accounting, internal control, funds flow, financial reporting, and auditing arrangements of the government borrower or other agency responsible for implementing Bank-supported loan operations.[1] Under OP/BP 10.02, Financial Management, the Bank requires that for each Bank-funded operation the borrower maintain acceptable financial management arrangements to provide reasonable assurance that the proceeds of the loan are used for the purposes for which the loan was granted.[2]
This chapter provides (1) an overview of the Bank’s project cycle, (2) a discussion of the elements of the Bank’s financial management practices as it prepares for and oversees lending, and (3) a presentation on some of the special arrangements related to Bank financial management that may be used in emergency operations. For a full discussion of the Bank’s response to emergencies, see Chapter 20, World Bank Response to Crises and Emergencies.
|
Stage
|
What it entails
|
|
Country Assistance Strategy
|
The World Bank project cycle begins with the elaboration of a Country Assistance Strategy. The Bank works with a borrowing country’s government and other stakeholders periodically to determine (or to update) how financial and other Bank assistance can have the largest impact. This is followed by the preparation of strategies and priorities for reducing poverty and improving living standards. Examples of nearly all the project documents mentioned in this section, including Country Assistance Strategies, are available on the Bank’s Web site.[3]
|
|
Project identification
|
Identified projects can be for infrastructure, housing, education, health, and government financial management, among others. The World Bank and government agree on an initial project concept and its beneficiaries, and the Bank’s project team outlines the basic elements in a Project Concept Note. Also generated during this phase are the Project Information Document and the Integrated Safeguards Data Sheet, which identifies environmental and social issues that may be raised by the project.
|
|
Project preparation
|
The borrower government and its implementing agency or agencies conduct feasibility studies and prepare engineering and technical designs, to name only a few of the work products required. Government contracts with consultants and other public sector companies for goods, works, and services, as necessary, not only during this phase but also later in the project’s implementation phase. Beneficiaries and stakeholders are consulted to obtain their feedback and enlist their support for the project. Due to the amount of time, effort, and resources involved, the full commitment of government to the project is vital.
Bank staff may determine that a proposed project could have environmental or social impacts that are included under the World Bank’s Safeguard Policies. If so, the borrower prepares an Environmental Assessment Report that analyzes the planned project’s likely environmental impact and describes steps to mitigate possible harm. An Environmental Action Plan may also be prepared. The recommendations are integrated into the project design. Chapter 21, Safeguard Policies for World Bank Reconstruction Projects, provides a detailed description of the Bank’s safeguard policies.
|
|
Project appraisal
|
Appraisal gives stakeholders an opportunity to review the project design in detail and resolve any outstanding questions. Government and the World Bank review the work done during the identification and preparation phases and confirm the expected project outcomes, intended beneficiaries, and the system that will be used to monitor progress. Once the Bank team confirms that all aspects of the project are consistent with World Bank operations requirements and that government has the institutional arrangements ready for implementation, the project is negotiated and is ready for approval.
|
|
Project approval
|
Once all project details are negotiated and accepted by both sides, the Bank prepares the Project Appraisal Document (for investment lending) or the Program Document (for development policy lending), along with other financial and legal documents, for submission to the Bank’s Board of Executive Directors for consideration and approval. The Project Information Document is updated and publicly released when the project is approved. When funding approval is obtained, conditions for effectiveness are met, and the legal documents are accepted and signed, the implementation phase begins.
|
|
Project implementation
|
The borrower government implements the project with funds from the World Bank. With assistance from the Bank, the implementing agency prepares the specifications for the project and carries out the procurement of goods, works, and services, as well as any environmental and social impact mitigation agreed to during preparation. Once under way, the implementing government agency reports regularly on project activities. The project’s progress, outcomes, and impact on beneficiaries are monitored by government and the Bank to obtain data to evaluate the results of the operation and the project. Government and the Bank also prepare a mid-term review of project progress. Full loan disbursement and project completion can take 1–10 years.
|
|
Project completion
|
As the project is completed, the World Bank and the borrower government document the results achieved, problems encountered, lessons learned, and knowledge gained from carrying out the project. The World Bank team prepares an Implementation Completion and Results Report, using input from the implementing government agency, co-financiers, and other partners and stakeholders. The information gained is used to determine if there is additional assistance needed to sustain the benefits derived from the project. The evaluation team also assesses how well the operation complied with the Bank’s operations policies, and accounts for the financial resources.
|
|
Project evaluation |
The Bank’s Independent Evaluation Group (IEG) assesses the performance of a selection of projects every year, measuring outcomes against the original objectives, sustainability of results, and institutional development impact. From time to time, IEG also produces Impact Evaluation Reports to assess the economic worth of projects and the long-term effects on people and the environment.
|
Assessments of financial management arrangements. The Bank assesses the adequacy of a borrower’s financial management arrangements during the preparation and implementation of each operation and requires the borrower to undertake appropriate measures to strengthen any identified weaknesses in its financial management systems and processes.
Interim financial reporting. The Bank normally requires a borrower to submit interim financial reports in a form agreed with the Bank.
Audited financial statements. The Bank requires that borrowers provide audited financial statements, within six months of the end of the reporting period, that reflect the activities of the operation supported by the Bank loan. The financial statements must be prepared using accounting standards acceptable to the Bank.[5] As for the audit, the auditing standards,[6] the scope of the audit, and the auditors who conduct it must be acceptable to the Bank as well. If the borrower fails to maintain acceptable financial management arrangements, or to submit the required financial reports by their due dates, the Bank can take action against the borrower.
Project implementation. During project implementation, financial management staff review the continuing adequacy of a borrower’s financial management arrangements. The extent, manner, and timing of these reviews is decided by the Bank on the basis of risk and actual implementation performance. In reviewing the arrangements, financial management staff undertake, as necessary, visits to project locations to meet with appropriate project staff, observe the performance of the financial management system, and check the application of controls or individual transactions. Financial management staff also (1) monitor the receipt and the timeliness of, (2) acknowledge receipt of, and (3) review the interim and annual audited financial statements that the borrower is required to provide. They pay particular attention to the quality of the auditor’s performance and the substance of the audit report findings.
When financial management staff note deficiencies in the arrangements, including failure to send timely audited financial statements to the Bank, poor auditor performance, or indications in the audit of weak internal controls, they discuss these matters with the borrower and make recommendations to the Bank country director. The borrower is notified of any actions taken by the country director.
Project completion and evaluation. Significant financial management performance issues during implementation are recorded in the Implementation Completion and Results Report.
Harmonization. The Bank is committed to harmonizing its financial management arrangements with other donors and aligning these around a country’s own systems. Accordingly, Bank staff will seek out opportunities for “delegated cooperation” (where one donor places reliance on the work of others) and ensure that, as far as possible, particularly in cases where multiple donors are involved in co-financing the same project or program, common arrangements are agreed to among all donors and government. Where a project is funded jointly by the Bank and other donors—a common situation for emergency operations—the Bank will seek to agree, to the extent practicable, on common formats, content, and reporting periods for reports to be submitted to all donors.
Analysis of risk. The implementation arrangements satisfactory to the Bank and the extent of Bank involvement during implementation will be a function partially of the Bank’s evaluation of the risk of an operation. For various reasons, emergency operations may be evaluated as having higher risk.
The Bank’s financial management risk model is qualitative and based on principles embodied in internationally recognized good practices for risk management.[8] The financial management risk rating is expressed as high, substantial, modest, or low, and provides a benchmark against which various aspects of project design, supervision, and other actions that may be taken by the Bank can be established. The risk model incorporates the following concepts.
|
Risk
|
Description
|
|
Inherent Risk
|
Inherent risk arises from the environment in which the project is located. It is the risk that the project financial management system does not operate as intended due to such factors as country governance environment, rules, and regulations. Inherent risk comprises three elements:
|
|
Control Risk
|
The risk that the project’s financial management system is inadequate to ensure project funds are used economically and efficiently, and for the purpose intended. Control risk is measured for all six elements of financial management: budgeting, accounting, internal control, funds flow, financial reporting, and auditing.
|
|
Detection Risk
|
The risk that a material misuse of loan proceeds takes place and is not detected. Detection risk is lowered by (1) capacity-strengthening measures for the weaknesses identified as posing unacceptable levels of risk, and/or (2) increasing Bank supervision.
|
|
Residual Risk
|
Residual risk is the combination of the project’s inherent and control risks as mitigated by borrower control frameworks and Bank supervision.
|
As discussed above, OP/BP 10.02, Financial Management requires that, for each Bank-funded operation, the borrower maintain acceptable financial management arrangements that can provide reasonable assurance that the proceeds of the loan are used for the purposes for which the loan was borrowed. Consistent with this requirement, one of the guiding principles of OP/BP 8.00 is the provision of appropriate oversight arrangements, including corporate governance and fiduciary oversight, to ensure appropriate scope, design, speed, and monitoring and supervision of rapid response operations.[9]
For financial management staff, the main difference between preparing “normal” and rapid-response operations lies in the timing of the financial management arrangements. To respond quickly to an emergency, financial management staff streamline and simplify ex-ante requirements while relying more heavily on such ex-post requirements as additional fiduciary controls and reviews. They need to ensure that risk-mitigating measures suitable to available capacity are in place during implementation and, as appropriate, they may rely more heavily than usual on partner institutions. Key considerations are the following.
The table below shows some examples of financial management arrangements for operations under OP/BP 8.00.
|
Area |
Ex-ante arrangements |
Ex-post arrangements |
|
Budget |
· Support 100% financing of activities to avoid delays in counterpart financing. · Provide adequate funds for essential initial operations even if sound estimates are not completed. · Reevaluate existing operations to find “excess” funds that can be quickly mobilized for the emergency operation. · Encourage Bank and other donors to align reporting requirements with government’s cycle. |
Detailed budget can be prepared later. |
|
Accounting and reporting |
· Use existing reporting frameworks from government or other projects. · Use manual systems or computer spreadsheets until on-line systems can be implemented. · Use a commercially available off-the-shelf accounting package that is quick to install and easy to use, especially if technical support is available in-country. · Outsource accounting functions to private sector or international firms, as needed. · Use United Nations agencies/programs and/or local and international nongovernmental organizations with sufficient financial management capacity. · Simplify reports, limiting them to a list of expenditures. |
Disseminate project reports to the lowest level beneficiary possible to help build in social accountability. |
|
Staffing |
· Outsource key operations to provide the needed staff in the short run. The Terms of Reference (TORs) could include training and capacity development of country staff and systems so that, over time, the country is gradually able to assume full responsibility for the financial management aspects of the activities. · Use staff from other parts of the implementing entities of the same project or from other projects. |
Train staff, even those with a limited accounting background, on simple cash accounting to provide the minimum records to get things moving quickly. |
|
Internal controls |
· To compensate for weak controls in low-capacity environments, consider: · internal, concurrent audits conducted by government or outsourced to private firms; · additional controls exercised by independent persons from different parts of government, implementing entity, or community, to help ensure that duties are separated; that transactions are budgeted, authorized, executed, and recorded properly; and that services are delivered as specified; and · using financial management agents to review implementing entity transactions and/or to process transactions in the short run to help ensure due diligence; TORs could include training and capacity development of country staff and systems so that, over time, the country is gradually able to assume full responsibility for the financial management aspects of the activities. |
Increase reliance on interim audits and/or more frequent (3-month or shorter period) external audits, including requesting an opinion on the internal controls and on-agreed procedures. Conduct performance audits to track the execution of project activities and deliverables. |
|
Funds flow and disbursement arrangements |
· If country financing parameters allow, finance 100% of project expenditures and limit the number of expenditure categories to one, or at most two. · As much as possible, use retroactive financing and reimbursement of expenditures. · Use output-based disbursements.[11] · Ensure that the designated account[12] is funded quickly and adequately. · Use simplified report-based disbursements. · Pool financing with other donors/government. |
If necessary, the Bank may disburse primarily through direct payments. |
|
External audit |
· The frequency, scope, and quality of audits are extremely important factors in helping ensure that funds are used for the intended purposes. · In consultation with other sector and procurement colleagues, expand audit scope as needed to cover technical, institutional, and financial reviews. · When national audit institutions have weak capacity, complement their teams with private sector auditors to help improve the quality of the audit and also build capacity gradually. (See Chapter 19, Mitigating the Risk of Corruption, Annex 2, How to Do It: Conducting a Construction Audit, for an audit methodology that can be used for a concurrent or ex-post audit of a reconstruction project.) · In the short run, use international auditors in some projects to substitute for low country capacity. · For project preparation advances (PPAs), consider the use of annual audits. · Subject to procurement approval, amend contracts of audit engagements for existing projects (either in the same sector or in others) to cover the work of the emergency operation. |
Audits should be carried out more frequently than annually, and financial management staff should follow up closely with the project implementing entity in a shorter time frame (i.e., from 6 months to 45 days). |
[1]. The policies and procedures summarized here apply to all loans, credits, advances under the Project Preparation Facility, and grants financed from World Bank resources, including International Development Association grants and Institutional Development Fund and other Development Grant Facility grants, with the exception of Development Policy (previously known as adjustment) Loans and Guarantees. They also apply to recipient-executed grants financed from trust funds, unless the donor agreement has different terms.
[2]. See “Guidelines: Financial Management Aspects of Emergency Operations Processed under OP/BP 8.00” and “Financial Management in Operations Processed under New OP/BP 8.00: FM for TTLs,” January 16, 2008 (PowerPoint presentations), internal Bank documents.
[3]. World Bank, “Documents and Reports,” http://go.worldbank.org/H1Q3T60M80.
[4]. World Bank, 2007, OP 10.02 “Financial Management,” http://go.worldbank.org/YHF8Y8UF30 and BP 10.02 “Financial Management,” http://go.worldbank.org/26MM8GUCU0.
[5]. Accounting standards acceptable to the Bank include International Public Sector Accounting Standards issued by the Public Sector Committee of the International Federation of Accountants and the International Financial Reporting Standards/International Accounting Standards issued by the International Accounting Standards Board. The Bank may accept national accounting standards that it considers to be equivalent to international standards.
[6]. Auditing standards acceptable to the Bank include the Auditing Standards issued by the International Organization of Supreme Audit Institutions and the International Standards on Auditing issued by the International Federation of Accountants. The Bank may accept national auditing standards that it considers to be equivalent to international standards.
[7]. World Bank Financial Management Sector Board, 2005, “Financial Management Practices in World Bank-Financed Investment Operations,” internal Bank report.
[8]. In particular, Committee of Sponsoring Organizations (COSO), Enterprise Risk Management – Integrated Framework; , and International Federation of Accountants, ISA 315, Understanding the Entity and Its Environment and Assessing the Risks of Material Misstatement and ISA 330, The Auditor’s Procedures in Response to Assessed Risks. For further discussion of the COSO Framework, see Chapter 19, Mitigating the Risk of Corruption, Annex 1, How to Do It: Conducting a Corruption Risk Assessment.
[9]. See “Guidelines: Financial Management Aspects of Emergency Operations Processed under OP/BP 8.00” and “Financial Management in Operations Processed under New OP/BP 8.00: FM for TTLs,” 2008, World Bank PowerPoint presentations.
[10]. World Bank, n.d., “Guidelines: Financial Management Aspects of Emergency Operations Processed under OP/BP 8.00,” internal Bank report.
[11]. Global Partnership for Output-Based Aid, “Checklist for Designing Output-Based Aid Schemes,” http://www.gpoba.org/designing/index.asp.
[12]. The “designated account” is the account of the borrower that is held in a financial institution acceptable to the Bank and operated on terms and conditions acceptable to the Bank, into which the Bank disburses proceeds from the loan account.
| Public Procurement in World Bank Operations |
World Bank Procurement Assessment Process |
| Procurement Issues in Emergency Operations |
Characteristics of a Good Procurement System |
· Policy makers
· Lead disaster agency
· Financial specialists
· Project managers
Carrying out procurement efficiently under World Bank-financed projects is critical to good project implementation, to the attainment of the objectives of the projects, and to their sustainability. Equally, the Bank, as part of its developmental role, is interested in strengthening the capacity of its borrowers to administer public procurement in an effective and transparent way as part of sound governance and good project management.[1]
To this end, the Bank has established procurement rules to be followed by borrowers for the purchase of goods, works, and services required for the projects financed by the Bank, and procedures for Bank review of the procurement decisions made by borrowers. World Bank project teams are required as an integral part of project preparation and appraisal, to make an assessment of the capacity of the project implementing agency or project implementation unit to administer procurement. For a description of the World Bank project cycle, see Chapter 22, Financial Management in World Bank Reconstruction Projects.
Procurement can become particularly challenging in emergency (post-disaster and post-conflict) operations, even for a government with established procurement capacity. Therefore, assessment of procurement capacity takes on special importance in emergency operations. For a full discussion of the Bank’s response to emergencies, see Chapter 20, World Bank Response to Crises and Emergencies.
This chapter provides (1) a review of the Bank’s procurement policies and procedures, (2) a summary of the Bank’s procurement assessment process, and (3) a brief discussion of procurement issues that the Bank may need to address in emergency operations.
World Bank Operating Policies (OPs) establish the parameters for the conduct of operations and describe the circumstances under which exceptions to policy can be made. They are based on the Bank’s Articles of Agreement, the general conditions, and policies. Bank Procedures (BPs) explain the procedures and documentation required to carry out the policies set out in the OPs. This section summarizes OP/BP 11.00, “Procurement.” [2]
Competition, economy, and efficiency. Competition is the basis for economic and efficient procurement. The Bank prefers procurement methods that maximize competition. Procurement of goods and works normally requires the use of international competitive bidding, and, for the selection of consultants, it normally requires the use of quality and cost-based selection(QCBS). Some exceptions are permitted.
Eligibility to compete. Any firm from any member country is eligible to compete for Bank-financed contracts except in any of the following circumstances.
Domestic preference. To encourage the development of domestic industries, the Bank permits:
Transparency. Transparency is an essential part of the Bank’s efforts to ensure effective use of loan funds and to combat fraud and corruption. To promote transparency, the Bank:
Role of the borrower and the Bank. The borrower is responsible for all aspects of project implementation, including procurement. For each project, the Bank assesses the capacity of the implementing agencies to carry out the required procurement and determines the level of associated risk. The borrower prepares a procurement plan that covers the activities necessary to ensure that project procurement will be carried out efficiently and professionally. The Bank assists the borrower in planning for procurement, including preparation of the procurement plan, and it supervises and monitors procurement decisions throughout project implementation.
If a borrower fails to carry out procurement in accordance with the procedures agreed to in the Loan Agreement, the Bank can cancel the amount of the loan allocated to the goods, works, or services that have been misprocured. The Bank may also apply other legal remedies.
Country procurement assessments. The Bank and the borrower’s government together periodically assess the effectiveness of the borrower’s procurement system and identify reforms to address deficiencies in the system. The findings of this assessment are incorporated into the Country Assistance Strategy. This chapter includes a description of the country procurement assessment process, below,
Fraud and corruption. The Bank requires that borrowers and bidders observe the highest standards of ethics during the procurement and execution of Bank-financed contracts. Firms found to have participated in fraudulent or corrupt practices or activities are declared ineligible to be awarded future Bank-financed contracts, either indefinitely or for a stated period of time. If a representative of the borrower is found to be engaging in such corrupt or fraudulent practices, the Bank cancels the amount of the loan allocated to the contract in question, unless the borrower takes action to remedy the situation that is satisfactory to the Bank.
Procurement capacity assessment and planning. The PS assesses the capacity of the agencies that will implement the operation to carry out project procurement, and the risks associated with procurement under the operation. The PS uses the most current applicable Country Procurement Assessment Report (CPAR) for this assessment. If the assessment reveals deficiencies, the Bank works with the borrower to formulate an action plan to strengthen capacity (including training or technical assistance, as appropriate) and mitigate the identified risks.
As soon as the nature and main components of the proposed project are identified, the PS assists the borrower in preparing the project procurement plan for an initial period of at least 18 months, taking into account any technical, financial, or management constraints the borrower may be facing. The procurement plan, which is updated annually or as needed during project implementation, covers:
For projects for which the contracting schedule and specific contracts cannot be precisely defined, the procurement plan consists of a description of all administrative aspects of procurement and consultant selection, including:
Project appraisal and negotiations. During appraisal, the Bank develops a procurement supervision plan and agrees with the borrower on standard bidding documents to be used for the project. The Bank and the borrower also agree on any activities to strengthen the procurement capacity of the borrower during implementation. These agreements are incorporated in the Loan Agreement.
Project implementation. During project implementation, the Bank evaluates whether the borrower’s procurement actions comply with the provisions of the Loan Agreement, and monitors adherence to the procurement plan and progress with the strengthening of the implementing agency. If major deficiencies occur, corrective actions are proposed.
Role of Bank staff in procurement activities. In working with borrowers on procurement matters, Bank staff maintain strict neutrality and impartiality. Staff do not:
Allegations of fraud and corruption and misprocurement. Complaints alleging fraudulent or corrupt practices by a bidder, supplier, contractor, or consultant in the procurement process of a Bank-financed contract are referred by Bank staff to the Department of Institutional Integrity. When Bank staff determine that the borrower has followed procurement procedures that are not in accordance with those set out in the Loan Agreement, the borrower is notified in writing. The notice brings the violation to the borrower’s attention and advises that, if the situation is not rectified, the Bank may declare misprocurement. One of the key Bank specialists involved in these situations is the Regional Procurement Adviser. Bank procedures that apply in these cases are detailed in BP 11.00.
Purpose of the agency assessment. The objectives of the agency capacity assessment are similar to those of the country procurement assessment, specifically to:
The agency capacity assessment is carried out by a PS assigned to the project during the project preparation stage of the project cycle. The aim is to have the assessment and the agreed-upon action plan finalized by the time of project appraisal.
Scope of the agency assessment. The capacity review includes an assessment of the capacity of the agency to carry out all phases of procurement. Typically, it includes a review of the following:
Emergency operations may give rise to unique procurement issues. This is due to two situations in particular: (1) risks inherent in the post-disaster procurement environment, such as the scale of procurement and the time pressure under which it may be taking place; and (2) the complexity of the institutional arrangements, particularly if there are numerous funding sources and special arrangements, such as multi-donor funds.
These issues have been addressed in the broader context of reconstruction project financial management in Chapter 22, Financial Management in World Bank Reconstruction Projects. Included below is a list of specific measures that the Bank and the borrower government may want to consider to lower the risk and increase the efficiency of procurement in post-disaster reconstruction projects.
This not an exhaustive list of issues and the CPAR is customized to the issues present in each country, including the manner in which all the above actually work in practice.
[1]. World Bank, 2002, “Revised Instruction for Carrying out Assessment of Agency’s Capacity Assessment to Implement Procurement; Setting of Prior-Review Thresholds and Procurement Supervision Plan,” http://siteresources.worldbank.org/PROCUREMENT/Resources/Assessment-all.pdf. “Loan” in this Operating Policy/Bank Procedure means International Development Account (IDA) credits and IDA grants and Project Preparation Facility (PPF) advances to which the Bank’s Procurement Guidelines are applicable according to the provisions of the relevant agreement with the Bank for the credit, grant, or PPF advance, but excludes development policy lending, unless the Bank agrees with the borrowers on specified purposes for which the loan proceeds may be used. “Procurement” refers to the purchase of goods, works, or services (e.g., the hiring of consultants); “borrower” includes the recipient of a grant or PPF advance, or the project implementing agency, when it is different from the borrower.
[2]. World Bank, 2001, OP 11.00 “Procurement,” http://go.worldbank.org/Y66EAJUGL1 and BP 11.00 “Procurement,” 2001, http://go.worldbank.org/Z33TBIUH90.
[3]. World Bank, 2006, “Guidelines: Procurement under IBRD Loans and IDA Credits,” http://go.worldbank.org/RPHUY0RFI0.
[4]. World Bank, “Procurement Policies and Procedures,” http://go.worldbank.org/JXJZSH4F50.
[5]. World Bank, 2006, “Guidelines: Selection and Employment of Consultants by World Bank Borrowers,” http://go.worldbank.org/U9IPSLUDC0.
[6]. World Bank, 2006, Consulting Services Manual: A Comprehensive Guide to the Selection of Consultants (Washington, DC: World Bank), http://siteresources.worldbank.org/INTPROCUREMENT/Resources/2006ConsultantManual.pdf.
[7]. World Bank, “Assessment of Country’s Public Procurement System,” http://go.worldbank.org/RZ7CHIRF60.
[8]. World Bank, “Documents and Reports,” http://go.worldbank.org/L5OGDXGTR0.
[9]. World Bank, 2002, “Revised Instruction for Carrying out Assessment of Agency’s Capacity Assessment to Implement Procurement; Setting of Prior-Review Thresholds and Procurement Supervision Plan,” http://siteresources.worldbank.org/PROCUREMENT/Resources/Assessment-all.pdf.